Group of companies Lekhim continues to construct manufacturing and storage complex of the third manufacturing site Lekhim-Obukhiv LLC, Kyiv region, Obukhiv, 126А Kyivska Str.
Construction phases of the third manufacturing site
Lekhim-Obukhiv LLC, Kyiv region, Obukhiv, 126А Kyivska Str.
Year 2018
– connection of the first power supply input with capacity of 250 kW;
– design works are completed and specifications for connecting to gas distribution system are obtained;
– specifications for connecting to municipal water supply lines and sewage collection system are obtained;
– beginning of installation of external and internal gas pipeline.
Year 2019
– beginning of internal and external maintenance works in the premises of Block B for storage of medicinal products;
– assembly of the boiler station;
– development of the concept design of Blocks A and Б reconstruction for the creation of the manufacturing and storage complex;
– design works for connecting to municipal water supply lines and sewage collection system are completed;
– beginning of connecting to municipal water supply lines and sewage collection system;
– beginning of connection of the second power supply input with capacity of 1000 kW;
– beginning of the project documentation development (General Design and Contract Documents phases) of Blocks A and Б reconstruction for the creation of the manufacturing and storage complex;
– cold chambers for storage of thermolabile products with storage conditions 2-8 0С – 8-15 0С are installed in Block B (warehouse for storage of the medicinal products).
Year 2020
– manufacturing and storage complex is connected to the general system of gas supply;
– installation of heating system, water supply lines, sewage collection system, electric lightning, fire-extinguisher system and internal firefighting water system at the warehouse Block B is completed;
– installation of ventilation and air conditioning system at the warehouse Block B is completed;
– installation of the site utility lines of firefighting water system are completed;
– installation and connection to the municipal water supply lines and sewage collection system are completed;
– maintenance works at Block B are completed;
– execution of the supply contracts for main process equipment for manufacture of the medicinal products;
– start of gas supply and boiler station.
Year 2021
– commissioning of warehouse Block B is planned for January-February;
– maintenance works of Blocks А and Б and installation of utility systems are planned for Qtr 1-3;
– installation of the packaging line are planned for Qtr 2;
– commissioning of the packaging line and utility systems is planned for Qtr 4;
– commissioning of the first stage of production is planned for end of the Qtr 4 – beginning 2022.